Risk Assessment in ERP Projects Life Cycle: the Application of FMEA Approach

2014 ◽  
Vol 9 (11) ◽  
pp. 1888
Author(s):  
Youssef Zaitar
Keyword(s):  
2015 ◽  
Vol 26 (3) ◽  
pp. 389-406 ◽  
Author(s):  
Maria Francesca Milazzo ◽  
Francesco Spina

Purpose – The purpose of this paper is to quantify the human health impacts of soy-biodiesel production with the aim to discuss about its environmental sustainability. Design/methodology/approach – The integrated use of two current approaches, risk assessment (RA) and life cycle assessment (LCA), has allowed improvement of the potentialities of both in obtaining a more complete analysis. The implementation of a life cycle indicator for the assessment of the impacts on the human health, integrating the features of both approaches, is the main focus of this paper. Findings – It has been found that, although the biodiesel is a green fuel, it has some criticalities in its life cycle, which cannot be disregarded. In fact, even if biodiesel is essentially a clean fuel there are some phases, prior to the industrial phase, that can cause negative effects on human health and ecosystems. Practical implications – Results suggest some measures which can be adopted to substantially reduce human health impacts. Further alternative could be analysed in future to gain more insight about the use of biodiesel fuels. Originality/value – The estimation of the impacts of a process producing biodiesel has been made by using a novel approach. The novelty is associated with the calculation of the impacts on human health by using the transfer factors applied in RA. The use of such factors, properly modified in order to estimate the impacts on a wider scale than a site-dimension, allows defining a holistic approach, as LCA and RA are used as complete units but at the same time can be related to each other.


Author(s):  
Е.В. Докукина ◽  
Е.В. Парфенова

В работе исследуется один из возможных метод оценки риска дополнительных финансовых незапланированных затрат в рамках реализации проектов ракетно-космической отрасли, поскольку по различным причинам они не учитывались при определении технико-экономических показателей реализуемого перспективного проекта. Следовательно, предлагаемый метод позволяет на ранних стадиях проведения исследований оценить дополнительные затраты и учесть их влияние на конечные технико-экономические показатели перспективного проекта. Метод строится на основе статистического анализа затрат по этапам жизненного цикла и по проекту в целом. По итогам исследования сделан вывод о том, что риск дополнительных финансовых затрат может снизить эффективность проекта в полтора - три раза. The paper explores one of the possible methods for assessing the risk of additional unplanned costs for the implementation of a promising project. Under additional means costs that for some reason were not planned when determining the technical and economic indicators of the prospective project being implemented. The proposed method allows for the early stages of research to assess the additional costs and take into account their impact on the final technical and economic indicators of a promising project. The method is based on a statistical analysis of costs for the stages of the life cycle and for the project as a whole. The study concluded that the risk of additional costs may reduce the effectiveness of the project in one and a half to three times.


2015 ◽  
pp. 383-419 ◽  
Author(s):  
Daniel A. Eisenberg ◽  
Khara D. Grieger ◽  
Danail R. Hristozov ◽  
Matthew E. Bates ◽  
Igor Linkov

2018 ◽  
Vol 170 ◽  
pp. 01091
Author(s):  
Yuliya Anoshina ◽  
Valery Gusev ◽  
Svetlana Suchkova ◽  
Roman Gorshkov ◽  
Elena Smorodina

The purpose of the paper is to identify factor space influencing on the value of discount rate in the assessment of effectiveness of investment and construction projects. As a result of investigation, a general classification of investment and construction risks was drawn up, depending on influence of external and internal environment of the enterprise. The factor space, which is used for initial data of separate investment and construction projects, was identified. A general algorithm of risk assessment of investment and construction project is developed, taking into account the reasoned justification of the method used for discount rate calculation, with the possible application of the variable discount rate at different stages of project’s life cycle.


Sign in / Sign up

Export Citation Format

Share Document